How long does a UPS installation take?

This depends on the size of the system and the electrical works required. A smaller single-phase UPS can often be installed and commissioned within half a day or one day if a hardwired external maintenance bypass is also installed. We often send the maintenance bypass to site for pre-installation to speed up the project. A larger 3 phase or parallel system with new switchgear, battery racks or generator interfaces is usually planned over 3-5 days. Every project starts with a site survey, after which we provide a programme of works with timescales alongside the costed proposal.